Project management case study

Based on the following information, create in Microsoft Project, a WBS and then an AON.  Add at least 4 milestones.  Now add a lag of two days to an activity on a noncritical path.
There are five employees involved in these activities.  Assign the tasks to people and create their pay rate, then add a few material resources, and then check to be sure that no one and no equipment is over assigned.  No human can work more than eight hours in a day, nor 40 hours in a week.
Create a Gantt chart to show that you are on time ten days into the project, and another to show that you are late by 2 days.
Now adjust the work week from five days (All of the figures are based on an 8 hour day, working Monday to Friday) to seven days a week, but no one person can work more than 40 hours in any week.  Print out the new ANO and Gantt chart.
Create a split view.
What is the baseline plan?  What is the cost of the project?
 
Activity           Preceding activities     Best                 Likely              Worst              TE
 
A                                 –                       12                    15                    25                    16
 
B                                 A                     4                      6                      11                    7
 
C                                 –                       12                    12                    30                    15
 
D                                 B, C                 8                      15                    20                    15
 
E                                  A                     7                      12                    15                    12
 
F                                  E                      9                      9                      42                    15
 
G                                 D, E                 13                    17                    19                    17
 
H                                 F                      5                      10                    15                    10
 
I                                   G                     11                    13                    20                    14
 
J                                   G, H                2                      3                      6                      3
 
K                                 J, I                   8                      12                    22                    13
 
The activities can be anything you want.  If you are lost, try constructing a house.

Looking for Discount?

You'll get a high-quality service, that's for sure.

To welcome you, we give you a 15% discount on your All orders! use code - ESSAY15

Discount applies to orders from $30
©2020 EssayChronicles.com. All Rights Reserved. | Disclaimer: for assistance purposes only. These custom papers should be used with proper reference.